Is the Machine Worth It? Four Numbers to Work Out
Labour, changeover and downtime, rework and material loss, and effective output. No preset payback promise: the estimate uses your real production data.

Labour
Headcount × hours per person × hourly labour cost. Compare the spend that can be reduced over the same period.
Changeover & downtime
Setup time + waiting time + hand-over time between processes. Count the effective hours lost to changeovers and waiting.
Rework & material loss
Rework + scrap + other non-conformance losses, converted to money, without counting the same loss twice.
Effective output
Good parts per hour × effective production hours. Assess added output separately to avoid double counting.
Estimated payback (months) = total project investment ÷ net monthly saving, after deducting added running and maintenance costs. The estimate depends on actual production data and is not a guaranteed payback.